What process involves overlapping project tasks to shorten project duration?

  1. Resource allocation

  2. Fast tracking

  3. Benchmarking

  4. Scope management

The correct answer is: Fast tracking

Fast tracking is the process that involves overlapping project tasks to shorten project duration. This approach allows project managers to identify activities that can be executed simultaneously rather than sequentially. By re-evaluating the project schedule and finding opportunities for concurrent task execution, the overall timeline can be reduced without necessarily decreasing the scope or altering the quality of the project deliverables. This method is particularly effective in complex projects where time is of the essence, and stakeholders are eager to see quicker results. However, it also comes with risks such as increased potential for resource conflicts or miscommunications, as team members may be required to balance overlapping responsibilities. Resource allocation refers to the distribution of available resources—such as personnel, equipment, or finances—to various project tasks, but it does not inherently involve the overlapping of these tasks. Benchmarking relates to comparing processes and performance metrics to industry bests or best practices from other organizations, and it does not directly influence the timing of project tasks. Scope management focuses on defining and controlling what is included and excluded from the project, which does not directly pertain to shortening project duration through task overlap.