What does crashing an activity involve?

  1. Eliminating non-essential tasks

  2. Adding more workers to reduce duration

  3. Extending the timeline for completion

  4. Involving stakeholders in decision-making

The correct answer is: Adding more workers to reduce duration

Crashing an activity refers to the process of accelerating the completion of a project task by allocating additional resources. This often includes adding more workers to a task, increasing work hours, or implementing other means that can specifically reduce the duration of an activity. By doing this, project managers aim to achieve deadlines more effectively and mitigate delays, particularly in critical path tasks. In contrast, other options do not accurately capture the essence of crashing. For instance, eliminating non-essential tasks refers to streamlining processes but does not directly involve speeding up any specific activity. Extending the timeline for completion would typically delay project progress, while involving stakeholders in decision-making is a project management best practice but does not inherently relate to the concept of crashing activities. Thus, adding more workers to reduce duration is the most fitting definition of crashing an activity.