Which element is NOT typically part of project closure?

  1. Performance reviews

  2. Releasing team members

  3. Archiving documents and plans

  4. Initiating project revisions

The correct answer is: Initiating project revisions

The correct answer is the option that identifies an action not usually taken during project closure. Initiating project revisions implies the need to alter or expand upon the project's outcomes or processes after the project has officially been completed. In project management, closure typically signifies that a project has been finished, and the focus shifts towards documenting what happened throughout the project, ensuring that all deliverables have been completed and finalizing all project-related activities. Typically, elements involved in project closure include performance reviews to assess the project outcomes against objectives, releasing team members to allow them to transition to new work once the project is wrapped up, and archiving documents and plans to preserve valuable knowledge and facilitate future projects. These activities support the acknowledgment of the project’s completion and ensure that lessons learned can be leveraged for future endeavors. In contrast, initiating project revisions signifies ongoing work and adjustments that would be more appropriately categorized within the execution phase rather than closure.