What is the primary objective of project integration management?

  1. To improve team dynamics

  2. To ensure stakeholder communication

  3. To begin with the end in mind and manage project authorization

  4. To allocate budget for activities

The correct answer is: To begin with the end in mind and manage project authorization

The primary objective of project integration management is to ensure that all aspects of a project are coordinated effectively. This includes making key decisions that align with the project's objectives from the outset. The concept of "beginning with the end in mind" reflects the need for a clear project vision, which facilitates managing project authorization and ensuring that all components work harmoniously towards achieving the desired outcome. By managing project authorization, the integration management process helps in prioritizing tasks, allocating resources efficiently, and responding to changes as the project progresses. This cohesive approach is vital for the successful execution of a project and meets the overarching goals set forth. Improving team dynamics, ensuring stakeholder communication, and allocating budgets are all important components of project management, but they fall under specific areas rather than encompassing the comprehensive focus that project integration management provides. Integration management serves as the backbone for synthesizing these various elements, ensuring that they collectively contribute to the final goals of the project.