What is acceptance criteria?

  1. A list of project deliverables

  2. Conditions for customer verification of deliverables

  3. Standards for project completion

  4. Guidelines for team performance

The correct answer is: Conditions for customer verification of deliverables

Acceptance criteria are specific conditions or benchmarks that must be met for a project deliverable to be considered complete and acceptable by the customer or stakeholders. They are crucial for ensuring that the final product meets the required quality standards and fulfills the customer's needs and expectations. By clearly defining these criteria ahead of time, a project team can focus on delivering what is necessary to satisfy both the project requirements and the customer's verification process. When stakeholders review the deliverables against these acceptance criteria, it provides a structured way to evaluate if the project outcomes align with the initially agreed-upon objectives. This process helps minimize misunderstandings and discrepancies, aiding in more successful project completions and customer satisfaction. In contrast, deliverables themselves refer to what is produced in the project and do not address the conditions for their acceptance. Standards for project completion might relate to overall metrics of success but do not specifically focus on customer verification. Similarly, guidelines for team performance would pertain more to how the team operates rather than the specific outcomes that need to be approved by the customer.