What are the three stages in the Master Production Schedule (MPS) development process?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Study for the Certified Supply Chain Professional (CSCP) Practice Exam. Prepare with multiple choice questions, each accompanied by hints and explanations. Get ready to ace your exam!

The three stages in the Master Production Schedule (MPS) development process consist of the draft of the plan, the capacity plan, and revisions to the plan.

The initial stage, the draft of the plan, involves creating a preliminary version of the schedule based on demand forecasts and other relevant data. This draft serves as a foundation that outlines what the organization intends to produce over a specified period.

The second stage, capacity planning, is crucial for ensuring that the necessary resources (such as labor, machinery, and materials) are available to meet the production requirements outlined in the draft. This phase assesses operational capabilities and confirms whether the proposed plan can be feasibly implemented based on existing resources.

Finally, revisions to the plan represent the iterative process of refining the initial draft by incorporating feedback from various stakeholders and making adjustments based on capacity constraints, supply chain variability, and changing market conditions. This stage ensures that the MPS aligns effectively with production capabilities and demand.

Together, these stages help to create a robust and practical MPS that facilitates effective production planning and scheduling.