What must be verified for a Master Production Schedule (MPS) to be considered workable?

Bottleneck capacity per item is optimal

The plan does not incur excess costs

All customer promises can be met

All of the above

A Master Production Schedule (MPS) is a critical component in production planning that outlines what products will be produced, in what quantities, and when they will be manufactured. For an MPS to be deemed workable, it is essential to confirm several factors that ensure the plan's effectiveness in achieving production goals. Verifying that bottleneck capacity per item is optimal is vital because any shortcomings in capacity at critical points in the production process can lead to delays and disruptions. These bottlenecks determine the maximum throughput and affect whether the production plan can be executed successfully. Additionally, ensuring that the plan does not incur excess costs is crucial for maintaining profitability. An MPS needs to balance production efficiency with cost-effectiveness, optimizing resource use while minimizing waste. Meeting all customer promises is fundamental as well, because an MPS that fails to fulfill customer demand can lead to dissatisfaction, lost sales, and a damaged reputation. The MPS must align production capabilities with customer expectations to maintain competitiveness and customer satisfaction. Considering all of these aspects together, ensuring that bottleneck capacity is managed, costs are controlled, and customer promises can be fulfilled affirms that the MPS is not only operationally feasible but also strategically sound, which is why the most comprehensive answer reflecting these necessities is

Next

Report this question